Pacific Coast Federation of Fishermen's Associations v. Gutierrez

UNITED STATES DISTRICT COURT EASTERN DISTRICT OF CALIFORNIA


March 4, 2009

PACIFIC COAST FEDERATION OF FISHERMEN'S ASSOCIATIONS/INSTITUTE FOR FISHERIES RESOURCES, ET AL., PLAINTIFFS,
v.
CARLOS M. GUTIERREZ, IN HIS OFFICIAL CAPACITY AS SECRETARY OF COMMERCE, ET AL., DEFENDANTS, AND SAN LUIS & DELTA MENDOTA WATER AUTHORITY, ET AL. INTERVENORS/DEFENDANTS.

The opinion of the court was delivered by: Hon. Oliver W. Wanger United States District Judge

ORDER GRANTING FEDERAL DEFENDANTS' MOTION FOR EXTENSION OF TIME OR, IN THE ALTERNATIVE, FOR RELIEF FROM COURT'S ORDER UNDER FED. R. CIV. P 60(b)

The Court's interim remedial order in this matter remanded the biological opinion on the "Operations Criteria and Plan" ("OCAP") for the coordinated operation of the Central Valley Project ("CVP") and State Water Project ("SWP") to the National Marine Fisheries Service ("NMFS"), requiring the remand to be completed by March 2, 2009. PCFFA v. Gutierrez, No. 1:06-cv-00245-OWW-GSA, Doc. 367 at 12 (July 18, 2008).

On January 21, 2009, the Federal Defendants informed the Court that NMFS no longer believed that it would be possible to complete a scientifically sound and legally defensible biological opinion by March 2, 2009, and moved to extend the deadline to June 2, 2009. Docket No. 419. The California Department of Water Resources and the Tehama-Colusa Canal Authority joined in the motion. Docket Nos. 420, 423. No party opposed the extension sought by the Federal Defendants, despite Plaintiffs' initial indication that they "reserved the right" to do so. Docket. No. 422.

NOW THEREFORE, having reviewed the memoranda of points and authorities submitted by the parties, the argument presented at the hearing held on February 23, 2009, and hearing no objection, the Court hereby enters the following Order on remand and injunctive relief:

The deadline for the issuance of a new Biological Opinion in this matter by the National Marine Fisheries Service, set forth in this Court's Findings of Fact and Conclusions of Law Re The Existence of Irreparable Harm During the Interim Period and Denying Plaintiffs' Requests for Emergency Interim Remedies Regarding Flows on Clear Creek and Gate Operations at Red Bluff Diversion Dam, Docket No. 367 (July 18, 2008), is extended from March 2, 2009 through and including June 2, 2009.

IT IS SO ORDERED.

20090304

© 1992-2009 VersusLaw Inc.



Buy This Entire Record For $7.95

Official citation and/or docket number and footnotes (if any) for this case available with purchase.

Learn more about what you receive with purchase of this case.