FTR International, Inc. v. Rio School District

California Court of Appeals, Second District, Sixth Division

January 27, 2015

FTR INTERNATIONAL, INC., Plaintiff and Respondent,
v.
RIO SCHOOL DISTRICT, Defendant and Appellant EAST WEST BANK, Intervener and Respondent.

[REHEARING GRANTED 2-24-15]

[CERTIFIED FOR PARTIAL PUBLICATION[*]]

Superior Court County of Ventura Nos. CIV201015, 01CC05901, 01HL05281, 204779, 205936, 207742, 207744, 207994, 208016, 223403) (Ventura County) William Q. Liebmann, Judge Mark S. Borrell, Judge

Page 839

[Copyrighted Material Omitted]

Page 840

[Copyrighted Material Omitted]

Page 841

COUNSEL

Baute Crochetiere & Gilford, Andrew M. Gilford, David P. Crochetiere; Negele & Associates, James R. Negele and Jonathan R. Hickman for Defendant and Appellant.

Kronick, Moskovitz, Tiedemann & Girard, Christian M. Keiner, Chelsea R. Olson and James P. Wiezel for Education Legal Alliance of the California Schools Board Association as Amicus Curiae on behalf of Defendant and Appellant.

Raisin & Kacvioglu, Bradley A. Raisin, Horwitz, Cron & Armstrong and John R. Armstrong for Plaintiff and Respondent.

Cox, Castle & Nicholson, Kenneth B. Bley, Randy P. Orlik, Susan S. Davis and Bradley A. Raisin, for Intervener and Respondent.

OPINION

GILBERT, P. J.

Public Contract Code section 7107 (section 7107) allows a public entity to withhold funds due a contractor when there are liens on the property or a good faith dispute concerning whether the work was properly performed. Here we conclude that a dispute over the contract price does not entitle a public entity to withhold funds due a contractor.

We disagree with Martin Brothers Construction, Inc. v. Thompson Pacific Construction, Inc. (2009) 179 Cal.App.4th 1401 [102 Cal.Rptr.3d 419] (Martin Brothers), which holds otherwise. We also conclude the doctrine of unclean hands does not apply to section 7107.

This case arises from a contract for the construction of a school. After the school was completed, the school district and its general contractor engaged in a decade-long legal battle. The result was a judgment for the contractor

Page 842

FTR International, Inc. (FTR) against the Rio School District (District) exceeding $9 million. District appeals.

We conclude: the trial court properly assessed penalties against District because it did not timely release retained funds required by section 7107.

We also conclude [[/]][*] the trial court erred in awarding fees for work not solely related to FTR's cause of action pursuant to section 7107.

We reverse and remand with instructions in the instances where the trial court erred and ...


Buy This Entire Record For $7.95

Download the entire decision to receive the complete text, official citation,
docket number, dissents and concurrences, and footnotes for this case.